Cameco Reports Update on Dewatering at Cigar Lake

Cameco Reports Update on Dewatering at Cigar Lake

August 13, 2008 Filed Under: Uranium Mining  

Cameco Corporation reports that remediation work at the No.1 Shaft at its Cigar Lake uranium project was temporarily suspended today after an increase in the rate of water inflow to the mine was observed.

“Remediation and dewatering of the No. 1 Shaft had been progressing smoothly up to this point,” said Tim Gitzel, Cameco’s chief operating officer. “An inflow at this rate is disappointing but our remediation plan, as approved by our joint venture partners, recognized the risk and included specific actions to be taken at various levels of inflow.”

No. 1 Shaft had been pumped down to 430 metres below surface when the increase was reported early Tuesday morning. Work in the shaft was suspended a few hours later. During the day, the inflow rate increased steadily to approximately 600 cubic metres per hour (m3/hr), which is beyond the range that can be managed while sustaining work in the shaft. The mine has a total depth of 500 metres and the mine underground workings are at the 480-metre level.

Work in the shaft has been suspended while the situation is assessed to determine the source and characteristics of the inflow, implications for planned remediation work and the impact, if any, on our planned production date.

Our current plan is to allow the water level in the shaft to rise to approximately 100 metres below surface. This will allow additional data to be gathered from instruments used to monitor groundwater conditions. As the water level rises, the rate of inflow will naturally diminish. This information will be analyzed to determine next steps. After this is complete, the water will be allowed to return to the natural equilibrium level.

As previously disclosed, the remediation plan for Cigar Lake includes options to address excess inflows including additional grouting from surface and ground freezing if necessary.

Pumping capacity is 1,000 m3/hr from four dedicated dewatering pumps installed in wells down to the 500-metre level. The water management system is limited by the treated water release limit of 550 m3/hr under the existing licence. There is a 74,000 cubic metre contingency storage pond at the surface that allows pumping at rates above the release limit for a limited period.

Cameco operates and owns 50% of the Cigar Lake project located in northern Saskatchewan. Cameco, with its head office in Saskatoon, Saskatchewan, is the world’s largest uranium producer. The company’s uranium products are used to generate electricity in nuclear energy plants around the world, providing one of the cleanest sources of energy available today. Cameco’s shares trade on the Toronto and New York stock exchanges.

Share this post